MONDAY  JANUARY 17, 2005 Archive  
 
Merino’s not ready yet

by Jennifer Reece

Reporter

HUDSON - A wall collapse at the new Merino’s Beer and Wine business downtown may cause more headaches for the project, which is already behind schedule.

Crews were scheduled for a Nov. 19 deadline to complete the first level of the building, though City Engineer Dave McCallops said it is now anticipated to take another several days to finish that work, regardless of the wall problem.

The total cost to the city for Merino’s move, which includes construction, relocating and loss of business expenses, will be in excess of $218,000.

McCallops said on Wednesday, as crews were working to finish a block wall to support an exterior ramp and stairs ascending to the second floor of the building, a wall collapsed.

No one was injured, and McCallops said he was not sure if the collapse would further delay the opening of the business, since the second floor is only intended to be used for storage.

McCallops said it is possible the first floor could be opened to shoppers, even though outside access to the second floor would not be finished.

The Merino family’s representative, Norman Grace, said Thursday that the owners never anticipated being out of business for this length of time.

“They [the city] have been doing what they said they were doing, but it has just taken a lot longer,” Grace said. “This has definitely impacted them [the Merinos]. They won’t be open for Thanksgiving; and the holidays are their most productive time of the year.”

Nearly two weeks ago, Council members expressed concern over the length of time the project has taken.

The city is paying the owners of Merino’s Beer and Wine $468 each day in lost business revenue until the building is finished and ready to open.

According to the original agreement between the city and Merino’s, the actual closure of the business due to the move was estimated to be between 30 and 50 days.

So far, the city owes Merino’s for more than 90 days of lost business.

The city owed the Merinos $234 per day for the first 30 days of construction and $468 for each day beyond that timeframe, according to the agreement signed by the Merinos and city officials.

Even before the wall collapse, McCallops said four structural items and one architectural problem contributed to the delays in getting the building completed.

The Merino’s building was moved from its previous location on North Main Street in mid-August to its new home on First Street.

The building could not stay where it was because a road extension was needed to tie into the new downtown redevelopment project, city officials said.

E-mail: jreece@recordpub.net

Phone: 330-688-0088, ext. 3145