MONDAY  JANUARY 17, 2005 Archive  
 
Merino’s costs city $468 a day

by Jennifer Reece

Reporter

HUDSON - The city is paying the owners of Merino’s Beer and Wine downtown $468 each day until the building is completed and ready to reopen for business.

If the project is completed by the end of this week, the total cost to the city of the move, which includes construction, relocating and loss of business expenses, would be about $218,000.

The construction of the project is behind schedule, city officials said at Tuesday night’s City Council workshop meeting.

According to the original agreement between the city and Merino’s, the actual closure of the business due to the move was estimated to be between 30 and 50 days. So far, the city owes Merino’s for more than 80 days of lost business.

City staff told Council that four structural items and one architectural problem have held up the process of getting the building completed.

City Engineer Dave McCallops said the project is expected to be completed Nov. 19, but noted the occupancy permit may not be issued on that same date.

Council members Tuesday expressed dismay at the amount of money the city is being asked to pay out, and the length of time the project has taken.

“It just seems to me that this is going very slowly,” said Council member John Jeffers.

Council President George Roth said the project seemed like a good idea when the contract was signed, but added it has gone on for too long.

“We need to bring this to a short conclusion,” Roth said.

Council member Dan Williams said he did not remember that the city had agreed to pay the Merino’s $468 each day the building was not finished after the initial 30 days, but acknowledged the city’s only other recourse may have been to take the property by eminent domain.

As of Nov. 3, the city owed Merino’s $30,420 - $234 for the first 30 days of construction and $468 for each day beyond that timeframe. As of Nov. 3, the city owed the Merinos’ for 50 days at the latter rate.

Those amounts are being paid to accommodate for lost business revenue established when the city negotiated a contract with Merino’s, city officials said.

To date, the city is expected to owe about $145,860 to Ver-Dick Builders for the Merino’s relocation, according to figures provided by the city.

Most of another $27,500 has already been paid to Klier Structural Movers for moving the structure to its new site.

In addition, the city has paid $1,840 to the Merinos’ accountant for negotiating the agreement. Another $420 is owed for moving inventory.

The city also owes the Merinos’ $4,789 for loss of business prior to the actual move, and $1,160 for advertising related to the reopening, according to city leaders.

The Merino’s building was moved from its previous location on North Main Street in mid-August to its new home on First Street. The structure was rotated 90 degrees and moved approximately 300 feet.

The historic portion of the building actually serves as the second floor at the new location.

The building could not stay on Main Street because of a road extension needed to tie into the downtown redevelopment project, city officials said.

The new location includes new electricity and plumbing, as well as a new bathroom with handicapped accessibility.

E-mail: jreece@recordpub.net

Phone: 330-688-0088, ext. 3145